Groundbreaking for the new Elementary School took place on March 2, 2018.   You can view the Construction Time Line here.

July 2019 Updates - Projects that were recently completed include the exterior brick, 1st coat of painting, and installation of the food service equipment.  On-going projects that are nearly complete include the fire suppression system, waterproofing, wood ceiling and walls, EIFS, and HVAC trim-out.  Projects that were recently started include electrical trim-out, plumbing trim-out, and mill-work.  Upcoming projects include finishing sidewalks and EIFS, continue exterior canopies, continue interior finishes, continue furniture install, apply 2nd coat of paint, and continue climatizing the building.  You can view the entire July construction project update letter here.

June 2019 Updates - Projects that were recently completed include waterproofing the exterior, MEP rough-in, and window frames.  On-going projects that are nearly complete include the fire suppression system, HVAC rough-in, exterior brick, roof gas lines, windows.  Other on-going projects include 1st coat of painting, ceilings, EIFS, and sidewalks, brick veneer, EIFS, and interior walls.  You can view the entire June construction project update letter here.  

May 2019 Updates - The roofing has been completed.  On-going projects that are nearly complete include the fire suppression system, HVAC rough-in, overhead plumbing, brick, waterproofing, interior framing, interior sheetrock, and OH electrical rough-in.  Other on-going projects include site lighting, EIFS, and interior painting.  You can view the entire May construction project update letter here.

March 2019 Updates - The structural steel, CMU Area S, storm shelter lid, exterior frame and sheathing are all complete.  On-going projects include the fire suppression system, HVAC rough-in, overhead plumbing, roofing, OH electrical rough-in, waterproofing, site lighting, and interior walls.  You can view the entire March construction project update letter here.

January 2019 Updates - The concrete paving has been completed.  On-going projects include the concrete slab, structural steel, and CMU Area S which are nearly complete.  Other on-going projects include the fire suppression and HVAC rough-in.  You can view the entire January construction project update letter here.

November 2018 Updates - On-going projects include the concrete slab, underground plumbing, underground electrical, and building steel erection.  You can view the entire November construction project update letter here.

October 2018 Updates - The grade beams were completed.  On-going projects include the concrete slab, site utilities, underground plumbing, and underground electrical.  We lost 6 days in October due to the weather.  You can view the entire October construction project update letter here.

September 2018 Updates - The lime stabilization was completed and the grade beams are nearly complete.  The site utilities, underground plumbing, and underground electrical are on-going.  The building steel material is on-site.  The weather impacted the construction progress and we lost 11 days in September.  You can view the entire September construction project update letter here.

August 2018 Updates - The piers were completed in August.  The site utilities and grade beams are on-going.  The next steps include the slab/foundation construction, paving and parking construction, and the steel construction.  We lost 3 days in August due to the weather impacting the progress of construction.  You can view the entire August construction project update letter here.

Construction Updates

RICE ISD
1302 SW McKinney, Rice, TX 75155
Administration - Phone: 903.326.4287 Fax: 903.326.4164
Elementary - Phone: 903.326.4151 Fax: 903.326.4900
Intermediate - Phone: 903.326.4190 Fax: 903.326.4620
High School - Phone 903.326.4502 Fax: 903.326.5042

  • Facebook Link
  • Twitter Link

 GO BULLDOGS!

webmaster@rice-isd.org